Haiti

August 2016 to March 2017 Haiti EPTISA Deputy Head of Mission Rehabilitation of Toussaint Louverture International Airport in Port au Prince
 
 Earthworks for the 1 million m2 platform, profiling, cut and fill, topsoil. •
 Widening of the runway to 45 m for ICAO classification of the airport in 4D •
 Rehabilitation of the sanitation of the entire platform •
 Longitudinal and transverse reshaping of the track by planing and reloading in GB.
 Coating two layers BBSG 0/14 and BBAD 0/14 of 5 cm •
 Construction of lateral and transverse drains.
 Management of the topographer and geotechnical team •
 Monitoring geotechnical tests •
 Work carried out at night outside air traffic.
 Company RAZEL-BEC •    
Amount of works: 23 million dollars financed by the IDB.