Comoros
July 1996 to July 1997 RFI Comoros on the island of Anjouan SECMO - OI Head of Mission for works control Rehabilitation of the Mutsamudu - Sima - Ponomi road (40 km) `
Control of the quantities of the DQE and verification of the financial implications to be reported to the Administration at the start of the work. Reinforcement in crushed 0 / 31.5.
Bi-layer coating
. Assessment of the asphalt road project and modifications.
Rehabilitation of village crossings and VRD development.
Protection wall against marine erosion, riprap of the banks.
Pavement sanitation works, drains.
Installation of alternative site lights for site areas limited to one lane.
Installation of mobile barriers painted in red and white.
Incorporation in the organization chart of the company of the responsible for road and personal safety (helmet use for example)
This manager is also responsible for the application of safety instructions by the company's subcontractors.
Verification of means of transport for company personnel and subcontractors
Installation of a temporary retarder across the road, either concrete or coated.
Site lighting during the night.
Installation of diversion in particular during construction of sanitation works.
Marking with paint of the provisional axis of the road under construction visible by day and by night.
For busy days (for example WE) mobilization of the coordinated police in conjunction with the Administration.
Company: COLAS
EDF financing;
Amount of works: 6.3 M. Euros